Campaign Logistics

In-person ALI / FIRR-2 Logistics Other Instruments
Summer 2024 Fall 2024 Winter 2025 Spring 2025 Summer 2025 Fall 2025 Jan 2026 Campaign +3 months
NRC to book Inuvik hanger PONEX Kickoff Meeting (in-person, all partners) INP, AMS, CFDC, DHL configuration for Convair finalized Establish ECCC Meteorologist team Test & calibrate ground-based instruments PONEX pre-campaign meeting (in-person, all partners) CAMPAIGN Return ground-based infrastructure
FIRR-2 redesign contract awarded ALI and FIRR-2 algorithm & instrument simulator development Reserve hotel(s) & vehicles Campaign implementation plan finalized, including list of on-site personnel All aircraft instruments with NRC for Convair integration Book commercial air flights for all on-site personnel QC of datasets & documentation of post-processing steps
ALI configuration for Convair finalized FIRR-2 redesign completed, received by NRC for integration Confirm ground-based site ALI redesign for Convair finalized, shipped to NRC for integration ALI and FIRR-2 instrument simulator finalized Test & calibration of Convair instruments Reporting to CSA, ESA
NWT research license submitted FIRR-2 with NRC for Convair integration Site planning visit to Inuvik Campaign validation rehearsal exercise NRC test flights Post-campaign follow-up meeting & data analysis plans
NRC-ECCC WHAFFERS Campaign (test FIRR-2) Ship instruments to Downsview for transport to Inuvik Backup and archive all datasets